Equinor and its Troll partners have decided to complete the Troll West Electrification project without installing a second electric export compressor on Troll C. The decision was announced on 15 October following a reassessment of production capacity, emissions reductions and project value.
Installing the additional compressor would have required modifications that could reduce Troll C production for up to 21 months. Equinor said avoiding that work is expected to make approximately 2.3 billion standard cubic metres of additional gas available to Europe during 2027 and 2028.
The revised scope retains substantial emissions savings. Partial electrification of Troll B and Troll C has reduced annual emissions by around 330,000 tonnes of CO₂, approximately 75% of the reduction originally envisaged.
The partnership will complete the project after commissioning the first electric export compressor on Troll C. Equinor said changing assumptions since the original 2021 development approval had increased the importance of retaining compressor capacity.
The company expects Troll C to continue operating until around 2050, while demand for the proposed additional compressor was expected to end in the mid-2030s.