SLB has secured a contract from OQ Exploration and Production for the Bisat-B Expansion Production Facility in Oman. Announced on 23 September 2026, the award covers design, engineering, procurement, construction and commissioning, followed by four years of operations and maintenance.

The facility is designed to handle gross fluids of 548,000 barrels per day. That figure describes total fluid processing capacity, rather than crude oil production alone. SLB said delivery is scheduled over 19 months.

The expansion extends a relationship that included the original Bisat-A and Bisat-B facilities in 2018 and 2020. Bringing construction and subsequent operations within one scope gives the project a continuous delivery model from engineering through start-up and ongoing facility support.