PetroTal has resumed development drilling at Peru’s Bretana field, starting horizontal well 25H on 21 September 2026. In its 23 September update, the company said the well was spudded approximately one week ahead of schedule.
The programme uses the higher-specification Estrella 2027 rig. Well 25H targets the Vivian formation at roughly 2,700 metres vertical depth, with an anticipated measured depth of around 4,300 metres. Drilling and completion are expected to take eight weeks at a cost of US$15 million.
PetroTal also reported improved water injection performance following stimulation work on two injection wells. Injection capacity averaged just over 190,000 barrels per day after the campaign.
The new well is the company’s first at Bretana since January 2025 and forms part of its effort to rebuild the field’s production base.