Equinor has raised the estimated cost of Norway’s Snøhvit Future project to NOK 26.5 billion in 2026 money, while retaining the planned start dates for onshore compression in 2029 and electrification in 2030.
The 7 October update compares with an estimate of just over NOK 20 billion in 2025 money announced last December. The original 2022 development estimate was NOK 13.2 billion, equivalent to NOK 15.2 billion at current value.
Equinor attributed the increase to greater-than-expected complexity at an operating LNG facility, operational challenges, weather and difficult rock conditions in the power-cable tunnel.
The project is around 60% complete. Its compressor module was installed in August, and work continues at Melkøya, on the tunnel and across the supplier network.
Onshore compression is intended to sustain Hammerfest LNG’s plateau production as reservoir pressure declines. Electrification is expected to reduce annual carbon dioxide emissions by 850,000 tonnes.
Equinor said targeted measures, risk management and coordination with the operating plant remain central to delivery. The partnership includes Petoro, TotalEnergies, Vår Energi and Harbour Energy.